Cement a 1 1 4 inch trap adapter into the tee.
Plumbing p trap in floor joists.
Note the photos show a recent bathroom remodel where we relocated the tub drain across several floor joists.
The floor joists are 2 x 10s and the joist cavity is insulated.
The ideal height is usually 18 inches above the finished floor but check your sink instructions to be sure.
The holes will have to follow a straight line that goes across the floor and has to either go up or go down so the pipe has a slope.
No room for 2nd floor tub trap.
You need to raise not only the trap but also the connection to the vent such that there s a maximum pitch of 1 4 per foot along the entire waste pipe between the trap and its vent.
This gives the strength for the weight of tub and person and raises the floor enough to install a regular trap for the tub.
I will accomplish two things by installing 2x8 joists where the tub is going.
Install a piece of 1x6 blocking and anchor the pipe with a strap.
The floor system is 2 10 joists spaced 12 inches on center.
During the layout stage plan to run the drainpipes parallel to the floor joists when possible.
Problem is the p trap almost touches the bottom of the joist cavity and is likely to freeze being very close to the exterior of the house.
Step 4 cut the holes.
When you run your pipes through a joist you will have to be careful with your work.
An important step in running drain lines occurs on paper before the actual plumbing begins.
I am installing a shower in a first floor location that is cantilevered out from the house.
The slope should be about 1 4 for each foot of pipe.
Install a sanitary tee facing into the room for the sink trap.
Prior to drilling holes in these floor joists we installed 3 4 inch plywood to each one.
Step 3 understand the joist slopes.
Erniecan tx i have this situation adding a bath upstairs in an old home.